Gary Casey
Gary Casey
Got it - thanks!
5 SP this sprint. Estimate 8SP remaining work; time-boxing to 5SP next sprint also
Time-boxing effort for this sprint to 4SP
@nickelskevin @cconstab drawing this to your attention as we've discussed this type of 'presence' functionality before
@nickelskevin @cconstab Now that some more time has passed ... How important do you think this now is from a usability standpoint?
Adjusting target to reduce the size of this issue.
Remaining: Once #350 and #370 have been merged then @gkc will resolve merge conflicts in their unit tests branch and merge in. Effort for #350 and #370 is included in...
No progress in PR29 sprint, more urgent unplanned work appeared
less important than continuing to enhance functional and end-to-end test coverage