Events might sometimes skip a day

Open boazbk opened this issue 4 years ago • 1 comments

When running a simulation, if there the next event will take place in more than a day, then there is a chance that time will advance (for example) from day 6 to day 8. This can be a problem if in the simulation there is weekly randomized testing going on in day 7.

I will be post a pull request soon that addresses this issue together with some other enhancements.

boazbk avatar Aug 28 '20 16:08 boazbk

The edits in my fork are probably too much for a pull request, but you can view them here https://github.com/boazbk/seirsplus

boazbk avatar Nov 16 '20 15:11 boazbk