redmine_better_gantt_chart icon indicating copy to clipboard operation
redmine_better_gantt_chart copied to clipboard

Additional columns

Open ghost opened this issue 14 years ago • 2 comments

I use this plugin, along with the #2024 patch, and find it to be a great addition to Redmine.

One suggestion I would like to make is the possibility of including an additional column to show the 'Assignee' of the issue. I know this information can be gained by hovering over the issue, but I think be able to see this for all issues would really help.

Is this something that can be done in this plugin, or would I need to contact the author of the #2024 patch?

Thanks,

Chris

ghost avatar May 06 '11 09:05 ghost

This info shal be printed of pdf and svg, so one can see which ressources are asseigned

cforce avatar Jan 26 '12 12:01 cforce

+1

additional (configurable?) collumns would be very desire. 'Assignee' is a must as gantt helps us in resource planning.

spaluc avatar Apr 19 '12 05:04 spaluc