Custom Interval in Worklog Export
Problem Statement
Some teams have irregular team meetings and the team members explain what they have done since the last meeting. Currently, as far as I know, only Month and Week are supported as report options. However, it would be so helpful if one could enter the start and end date of the report as input in a custom option.
:grey_question: Possible Solution
Add a custom button to the Worklog Export part and create the report based on the specified start and end time.
:arrow_heading_up: Describe alternatives you've considered
Right now, I try to either combine day-by-day reports or modify the monthly one.
:heavy_plus_sign: Additional context
--
Thank you very much for opening up this issue! I am currently a bit overwhelmed by the many requests that arrive each week, so please forgive me, if I fail to respond personally. I am still very likely to at least skim read your request and I'll probably try to fix all (real) bugs if possible and I will likely review every single PR being made (please, give me a heads up if you intent to do so) and I will try to work on popular requests (please upvote via thumbs up on the original issue) whenever possible, but trying to respond to every single issue over the last years has been kind of draining and I need to adjust my approach for this project to remain fun for me and to make any progress with actually coding new stuff. Thanks for your understanding!
Hello there SMZ70! 👋
Thank you and congratulations 🎉 for opening your very first issue in this project! 💖
In case you want to claim this issue, please comment down below! We will try to get back to you as soon as we can. 👀
For more open ended discussions and/or specific questions, please visit the discussions page. 💖
Thanks for opening this up! Just allowing to specify a start and an end date might be a good start. PRs are welcome!
This issue has not received any updates in 90 days. Please comment, if this still relevant!
Would like to mark this as still relevant! Will attempt a PR in future but will take considerable time with my current lifestyle
This issue has not received any updates in 90 days. Please comment, if this still relevant!
I'd dare say this is still very valid. I ended up here searching for a possibility to do a worklog export for a single day (as opposed to month and week). A custom range set to start and end on the same day would also be a fit. Filtering out from a week's CSV export doesn't help because tasks spanning multiple days show the sum of all days on this task. But I need the time spent on a task on a specific day even when it spans multiple days.
This issue has not received any updates in 90 days. Please comment, if this still relevant!
Still relevant