The parent task is not sent to tyme

When I create a task in the project, this task is sent to tyme,however, if this task has subtasks, the subtasks will eventually be sent as tasks to the tyme,The parent task is not sent to tyme
I am a designer,I can`t solve this problem independently, so I sent this issue
Hope to get your help
I think I used this approach intentionally. Because Tyme dose not support multi-level hierarchy, it's impossible to replicate the structure to Tyme. Thus I consider the subtasks as "minimal workable unit", which should be time-logged, instead of the parent one. Currently I do not use this setup anymore, but if you still want to add both parents and child task to Tyme, I can try look into it. It should be easy.