fix: Production Plan, pending qty is wrong if alternative UoM is used
Production plan incorrectly calculates pending qty if uom is not main uom in sales order.
Sales Order:
Before (Production Plan, Assembly Items ):
After (Production Plan, Assembly Items ):
PS1: It's now calculates the pending qty with respect to conversion factor in sales order. PS2: I only corrected Sales Order part. Material Request handle the calculation in the database and it seems correct.
Please provide enough information so that others can review your pull request:
Explain the details for making this change. What existing problem does the pull request solve?
Screenshots/GIFs
Super news. Thanks.
@TurkerTunali Please fix Linters issue
This pull request has been automatically marked as inactive because it has not had recent activity. It will be closed within 3 days if no further activity occurs, but it only takes a comment to keep a contribution alive :) Also, even if it is closed, you can always reopen the PR when you're ready. Thank you for contributing.
This pull request has been automatically marked as inactive because it has not had recent activity. It will be closed within 3 days if no further activity occurs, but it only takes a comment to keep a contribution alive :) Also, even if it is closed, you can always reopen the PR when you're ready. Thank you for contributing.