Work Order -> Job Card Time Log Issue
Job Card Against Work Order
- WorkOrder Has 10 Qty .
- Bom has 3 Operation and operation batch size 1 and operation time 10min.
- Submit the work order it create 30 job Card.
- In Job Card -> Time Log table->Time In mins was calculate for 10qty operation time for single jobcard.
- Operation Time should calculate 1qty operation time for single jobcard.


Information about bug

Version
v13
Module
manufacturing
Version
ERPNext: v13.16.1 (version-13)
Frappe Framework: v13.16.0 (version-13)
Installation method
manual install
Relevant log output / Stack trace / Full Error Message.
No response
Code of Conduct
- [X] I agree to follow this project's Code of Conduct
Hi @sowndharya998
I tried this in v13/14 and the results are different when I submit the Work Order only 3 Job cards get created as I have 3 Operations in the BOM. Please let me know if I missed something.
-
BOM

-
BOM Operations and Items

-
Work Order Operations

-
Job Card Quantity to Produce

@sowndharya998 by default the batch size is 1 and the BOM you have created to manufacture Single Unit of Finished Goods therefore system has set the operation time as 100. This is by design and not an issue.