Task - add remaining work 0,5
Issue At the moment, the remaining work field is not included at all when creating a template for a task. It can be added manually. But the moment 0.5 is entered, this is converted to 5 with the 1-click function. So the 0, is ignored in this field.
Desired solution Ability to include 0.5 in the remaining work field within the 1-click functionality.
Update: We noticed that the issue is not for Apple Edge, but is for Windows Edge. We tried with a . and , but both options are getting changed to 5 in stead of 0,5
I would really appreciate a solution.