Delta Tech: MRP Edit Components
I have On Track by Lots option on Finish Good to be produced, when i changed the component with this module the total consumption quantity on Work Center changes automatically on 1 qty for all components and when i try to done the MO it gives an error
Hi,
Please give us more details about your workflow (work center and operations configuration etc). Some print-screens should be usefull.
Also, what version of Odoo are you using? On v12 should work fine (see attached)
When you change the component
i have change 3 3rd last component
Now i have planned a order on Work centre, now you can see the difference between the BOMS to be consumed
Im using this on odoo V-13