Upgrading to 18.03, added manually the llx_project_task_time table. Report seems to send empty result. I tried create new project + new entry in task and time. Everything works fine except report.

Module Version 4.6.7 Dolibarr 18.03 with PHP 7.4.3-4 and Apache 2.4.41 on Ubuntu 20.04 MySql Server 8.035 on Ubuntu 20.04

fjfleury avatar Nov 14 '23 11:11 fjfleury

Hello, Same problem. Does anyone have a solution? Thanks

Griotsky avatar Nov 22 '23 14:11 Griotsky

After a bit of head banging, I saw that the v. 18 release notes changes how Dolibarr handles task time. Rather than the unique table, "projet_task_time," which is missing in v. 18 (thus the errors on the timesheet page), v. 18 uses a new table that tracks times for a variety of elements. From the v. 18 changelog:

NEW: element time integration code + SQL NEW: tables: llx_element_time to store time spent on several elements (mo, ticket...)

I am not adept enough at coding Dolibarr yet to make the required change, but it looks like until this module is changed to use the new version of time management, it will remain broken.

whp-jeffm avatar Dec 14 '23 19:12 whp-jeffm

should be fixed a long time ago

delcroip avatar Jul 05 '24 22:07 delcroip