DAOS-14517 test: Changing test yaml to use storage auto
Test failed in CI complaining of no bdevs. Hence, changed yaml file to use storage: auto.
Test-tag: test_daos_vol_bigio Test-repeat: 5
Before requesting gatekeeper:
- [ ] Two review approvals and any prior change requests have been resolved.
- [ ] Testing is complete and all tests passed or there is a reason documented in the PR why it should be force landed and forced-landing tag is set.
- [ ]
Features:(orTest-tag*) commit pragma was used or there is a reason documented that there are no appropriate tags for this PR. - [ ] Commit messages follows the guidelines outlined here.
- [ ] Any tests skipped by the ticket being addressed have been run and passed in the PR.
Gatekeeper:
- [ ] You are the appropriate gatekeeper to be landing the patch.
- [ ] The PR has 2 reviews by people familiar with the code, including appropriate watchers.
- [ ] Githooks were used. If not, request that user install them and check copyright dates.
- [ ] Checkpatch issues are resolved. Pay particular attention to ones that will show up on future PRs.
- [ ] All builds have passed. Check non-required builds for any new compiler warnings.
- [ ] Sufficient testing is done. Check feature pragmas and test tags and that tests skipped for the ticket are run and now pass with the changes.
- [ ] If applicable, the PR has addressed any potential version compatibility issues.
- [ ] Check the target branch. If it is master branch, should the PR go to a feature branch? If it is a release branch, does it have merge approval in the JIRA ticket.
- [ ] Extra checks if forced landing is requested
- [ ] Review comments are sufficiently resolved, particularly by prior reviewers that requested changes.
- [ ] No new NLT or valgrind warnings. Check the classic view.
- [ ] Quick-build or Quick-functional is not used.
- [ ] Fix the commit message upon landing. Check the standard here. Edit it to create a single commit. If necessary, ask submitter for a new summary.
Bug-tracker data: Ticket title is 'daos_vol/bigio.py:DaosVolBigIO.test_daos_vol_bigio - 200 GB NVMe requested for pool but config has zero bdevs' Status is 'In Progress' Labels: 'ci_impact,test_fix,triaged,weekly_test' https://daosio.atlassian.net/browse/DAOS-14517
Test stage Functional Hardware Large completed with status UNSTABLE. https://build.hpdd.intel.com/job/daos-stack/job/daos//view/change-requests/job/PR-13208/2/testReport/
Test stage Functional Hardware Large completed with status FAILURE. https://build.hpdd.intel.com//job/daos-stack/job/daos/view/change-requests/job/PR-13208/3/execution/node/1279/log
Test stage Functional Hardware Large completed with status FAILURE. https://build.hpdd.intel.com//job/daos-stack/job/daos/view/change-requests/job/PR-13208/4/execution/node/1195/log
Test stage Functional Hardware Large completed with status FAILURE. https://build.hpdd.intel.com//job/daos-stack/job/daos/view/change-requests/job/PR-13208/5/execution/node/1195/log
Bug-tracker data: Ticket title is 'daos_vol/bigio.py:DaosVolBigIO.test_daos_vol_bigio - 200 GB NVMe requested for pool but config has zero bdevs' Status is 'In Progress' Labels: 'ci_impact,scrubbed,test_fix,triaged,weekly_test' https://daosio.atlassian.net/browse/DAOS-14517
Ticket title is 'daos_vol/bigio.py:DaosVolBigIO.test_daos_vol_bigio - 200 GB NVMe requested for pool but config has zero bdevs' Status is 'In Progress' Labels: 'ci_impact,scrubbed,triaged,weekly_test' https://daosio.atlassian.net/browse/DAOS-14517
Test stage Functional Hardware Medium completed with status UNSTABLE. https://build.hpdd.intel.com/job/daos-stack/job/daos//view/change-requests/job/PR-13208/7/testReport/
Test stage Functional Hardware Large completed with status FAILURE. https://build.hpdd.intel.com//job/daos-stack/job/daos/view/change-requests/job/PR-13208/7/execution/node/1418/log
Test stage Functional Hardware Large completed with status UNSTABLE. https://build.hpdd.intel.com/job/daos-stack/job/daos//view/change-requests/job/PR-13208/8/testReport/
Test stage Functional Hardware Large completed with status FAILURE. https://build.hpdd.intel.com//job/daos-stack/job/daos/view/change-requests/job/PR-13208/9/execution/node/1405/log
Test stage Functional Hardware Large completed with status FAILURE. https://build.hpdd.intel.com//job/daos-stack/job/daos/view/change-requests/job/PR-13208/10/execution/node/1408/log
Closing as https://github.com/daos-stack/daos/pull/14523 is landed.