Task effort is not updated
Hi Bryntum team, we observed this confusing behavior when testing calendars: This project has a calendar with 8h/day work time and the task 10h/day with one assigned resource and "schedulingMode": "FixedDuration".
After setting 'ignoreResourceCalendar' to true, the assignment effort increased to 80 hours, while the task effort remained unchanged at 64 hours. We expect these two value to align in this case.
Attached, you'll find a demo for testing purposes. We're uncertain if the observed behavior is intentional, and we're seeking further insight. Could you please provide us with more information? Thanks a lot!
Best regards, Xianer