We can calculate the resource cost from their payment rate and assignments, however, sometimes there is just a fixed cost per task which does not depend on the resource load or task duration. It would be nice to be able to account for this fixed resource cost .

dbarashev avatar Apr 13 '21 11:04 dbarashev

See also this topic on the support portal: https://help.ganttproject.biz/t/resource-total-cost-is-0/2879