@tdonohue we can start to work on that. Right now it is still unclear how to solve the issue so the estimation needs to be refined after further investigation but...

@tdonohue we are interested in take also the angular part as we are working on the REST part. Our estimation is 3-4 days (28 hours)

this should take 4-8 hours with manual testing. Adding IT/Unit on this part of the code base could be very costly

we (at 4Science) are interested in working on that. It is not trivial as REST/contract changes are also required (estimation 16 hours). Min/max needs to be returned by the REST...

in dspace-cris we solved this issue introducing an extra permission evaluator that keep in consideration also facts about the item looking to the metadata (authors, editors, etc) - submitter and...

we (4Science) are interested in working on that. An estimation is currently not available, it would be probably in the range of 3-10 days we can provide a more accurate...

reviewed today: the current behavior has been improved as only a limited number of pages are listed. The current implementation show an "architectural" issue as angular should be NOT able...

we want to note that the subscription functionality have been extended and implemented in DSpace-CRIS 7. If what we have done in DSpace-CRIS is of interest of the DSpace community...

@tdonohue we are ready to start working on that, it is not a trivial task and estimation can be provided only after some extra analysis. Our best guess at the...

we (at 4Science) can work on that. REST implementation (to return a 422 instead than the 500) would take 6 hours. The constraint could be relaxed to a wider size...