Summary

Paramter & unit PyPSA-Eur NEP 23 NEP 21 ACER 23 average ACER 23 Q3 Vrana & Härtel (2023) CIGRE (max) CIGRE (min) Pathway 2.0
AC overhead (€/MW/km) 442 1325-1384 736 371 481 - 250 130 -
AC underground (€/MW/km) - 4711 3386 771 821 - - - 1200
AC submarine (€/MW/km) - - - 1182 1488 - - - 7005
DC overhead (€/MW/km) 442 - 1000 371 481 - 330 180 -
DC underground (€/MW/km) - 3300-3800 3250 771 821 870 - - 3690
DC submarine (€/MW/km) 1008 - - 653 741 1159 1900 1270 2140
DC inverter pair (€/kW) 166 - 600 150 193 - 316 180 -

NEP 2023

https://www.netzentwicklungsplan.de/sites/default/files/2023-03/230321_NEP_Kostenschaetzung_NEP2037_2045_V2023_1.Entwurf.pdf

auf 2x1.698 GW (2 circuits) = 3396 MW

AC-Freileitung: 380-kV HTLS-Parallelneubau (Doppelleitung, 2 Stromkreise) 4,7 Mio. EUR / km 380-kV Neubau in neuer Trasse (Doppelleitung, 2 Stromkreise) 4,5 Mio. EUR / km

1383.98 EUR/MW/km 1325.09 EUR/MW/km

AC-Erdkabel: 380-kV Neubau in neuer Trasse 16 Mio. EUR / km

4711.43 EUR/MW/km

DC-Erdkabel: 320-kV Neubau in neuer Trasse (1 GW ohne metallischen Rückleiter) 3,5 Mio. EUR / km 525-kV Neubau in neuer Trasse (2 GW mit metallischem Rückleiter) 7,6 Mio. EUR / km 525-kV Neubau in neuer Trasse (2 GW) 6,6 Mio. EUR / km

3500 EUR/MW/km 3800 EUR/MW/km 3300 EUR/MW/km

Assumptions for retrofit suggest similar cost of AC-Freileitung and DC-Freileitung.

Underground assumptions could also be used for submarine assumptions.

NEP 2021

https://www.netzentwicklungsplan.de/sites/default/files/2023-02/NEP_2035_2021_1_Entwurf_Kostenschaetzungen_0.pdf

AC-Freileitung: 380-kV-Neubau Doppelleitung 2,5 Mio. € / km Neubautrasse, Hochstrom

736 €/MW/km

AC-Erdkabel: Teilverkabelung Neubau 380-kV-Doppelleitung 11,5 Mio. € / km inkl. Kabelübergangsanlage

3386 €/MW/km

DC-Freileitung: Neubau DC-Freileitung 2,0 Mio. € / km Neubautrasse mit 2 Systemen mit je 2 GW

500 €/MW/km assuming 4GW

DC-Erdkabel: Neubau DC-Erdkabel 6,5 Mio. € / km Neubautrasse mit 1 x 2 GW

3250 €/MW/km

DC-Konverterstation: DC-Konverterstation 0,3 Mio. € / MW pro Konverterstation

ACER

https://www.acer.europa.eu/sites/default/files/documents/Publications/ACER_UIC_indicators_table.pdf

Overhead line (million EUR/km) 380-400 kV 2 circuits 1,261 / 1,635 Underground cable (million EUR/km) 300 - 500 kV 1 circuit 1,309 / 1,394 Submarine cable (million EUR/km) AC 2,007 / 2,527- assume 1 circuit? Submarine cable (million EUR/km) DC 1,108 / 1,258 - assume 1 circuit? HVDC converters (million EUR/kWh) 0,150 / 0,193 - unit should be MEUR/kW?

average

371.32 EUR/MW/km 770.90 EUR/MW/km 1181.98 EUR/MW/km 652.53 EUR/MW/km 150000 EUR/MW

Q3 values

481.44 EUR/MW/km 820.97 EUR/MW/km 1488.22 EUR/MW/km 740.87 EUR/MW/km 193000 EUR/MW

Langfristszenarien

https://www.langfristszenarien.de/enertile-explorer-wAssets/docs/Consentec-TUBER_BMWK_LFS3_Webinar_Netze_T45_final_v2.pdf

"Kostenansätze entsprechend ÜNB-Annahmen im NEP bzw. Erfahrungswerten Consentec"

TYNDP

TYNDP not published, at least nowhere to be found ?!

DEA

only has distribution level assumptions, no transmission level

Vrana / Härtel

https://pdf.sciencedirectassets.com/271091/1-s2.0-S0378779617X00072/1-s2.0-S0378779617302572/dx.doi.org/10.1016/j.epsr.2017.06.008

https://doi.org/10.1109/EEM58374.2023.10161832

OverHead Lines (OHL) are not included in the new cost model, as only a few HVDC overhead lines are being built or planned in Europe

Rating of 2.2 GW

submarine:

1.061 M€/GW/km 2.784 M€ assuming 2.2 GW and 100km length 0.248 M€/km / 2.2 GW

1061 €/MW/km + 112.72 €/MW/km + 12.65 €/MW/km = 1159.37 €/MW/km

underground

0.672 M€/GW/km 2.784 M€ assuming 2.2 GW and 100km length 0.408 M€/km / 2.2 GW

672 €/MW/km + 185.45 €/MW/km + + 12.65 €/MW/km = 870.1 €/MW/km

technology-data

HVAC overhead investment 442.1414 EUR/MW/km HVDC overhead investment 442.1414 EUR/MW/km HVDC submarine investment 1008.2934 EUR/MW/km HVDC inverter pair investment 165803.0398 EUR/MW

Pathway 2.0 Techno-economic data

https://zenodo.org/records/10101328

Screenshot from 2024-03-13 17-26-33

CIGRE

(e-mail Strommarkttreffen)

https://groups.io/g/strommarkttreffen/message/5721

globaler Wertebereich

Cost (M€) DC OHL (M€/km/GW) DC USC (M€/km/GW) AC OHL (M€/km/GW) AC/DC Converter (M€/GW for one SS) AC/AC Back to Back SS (M€/GW for one SS)
Max 0.33 1.90 0.25 158 158 158
Min 0.18 1.27 0.13 90 90 90