Sprint Poker: "Estimate phase is already complete" error message
This message appears when the estimate phase is completed. We consider it completed when all stages are completed. We mark a stage completed when the facilitator moves to the next stage after it. Since this cannot happen for the last stage in a Sprint Poker meeting, to reach this state you have to either
- navigate through all issues and then remove the last non-completed issue
- move a completed issue to the last position and move through the others
This way all stages can be completed without also ending the Poker meeting.
I don't think this logic is correct given the async use case and at the moment we don't have any phases after estimate, so there is no reason to check for isPhaseCompleted in this case.
The error came up in a support case [slack thread]
Acceptance criteria
- [ ] voting in Sprint Poker is possible even when all stages are completed, i.e. don't check for
isPhaseCompleted('Estimate'...)
Similar issues: #6755 #6890
Still a thing, was just reported by a customer
Stale issue
I know this is still a thing, but I'm going to icebox it as it went stale again. If it gets reopened, let's really fix it.