[BUG] Milestone shifted by -1 in calendar
If you have problems with the installation please use our community forum
What set up are you using
- [ ] Cloud Hosted Version
- [x] Self Hosted
Describe the bug In the calendar, the milestone dates are shifted by -1 day.
To Reproduce Steps to reproduce the behavior:
- Add a milestone
- Choose a date start and end date
- Save
- Look on the calendar
- The date displayed on the calendar is shifted by -1
Expected behavior For example, if the milestone end and start dates are 02/15/24, on the calendar the milestone should appear on the date 02/15/24 and not 02/14/24.
Leantime Version 3.0.7
Server nginx/1.22.1
PHP / MySQL Version PHP 8.2.7 / 10.11.6-MariaDB-0+deb12u1 Debian 12
Additional context Add any other context about the problem here.