@knopers8 @davidrohr @aalkin if you could stress test a bit this i would appreciate.
In general, it seems to work OK. Is it possible to control the state of devices globally or only individually?
Also, it seems that the GUI hangs during exit when running with --completion-policy wait
, I am not sure if this is natural consequence of the option or not.
Can you update alidist? I think you need the new DebugGUI to fix that hang.
I will leave it compiling with new alidist overnight
it still hangs, see o2-qc-run-basic --completion-policy wait
as a reproducer
Error while checking build/O2/fullCI for beeb5454487c264f7976c27d10fde63881472d2c at 2023-10-14 02:17:
No log files found
Full log here.
Error while checking build/O2/fullCI for 0b08540a5f9c195dd0da911381cd817359f3a75e at 2024-02-08 06:41:
## sw/BUILD/O2-latest/log
c++: error: unrecognized command-line option '--rtlib=compiler-rt'
c++: error: unrecognized command-line option '--rtlib=compiler-rt'
## sw/BUILD/O2-full-system-test-latest/log
command alien-token-init had nonzero exit code 2
## sw/BUILD/o2checkcode-latest/log
--
========== List of errors found ==========
++ GRERR=0
++ grep -v clang-diagnostic-error error-log.txt
++ grep ' error:'
++ GRERR=1
++ [[ 1 == 0 ]]
++ mkdir -p /sw/INSTALLROOT/5fb830d1503fd69d1efb443a4f94625f810b022d/slc8_x86-64/o2checkcode/1.0-local1559/etc/modulefiles
++ cat
--
Full log here.
This is something that would be extremely helpful for the SSS debugging and testing. Would it be possible to resume the effort ?
This PR did not have any update in the last 30 days. Is it still needed? Unless further action in will be closed in 5 days.
REQUEST FOR PRODUCTION RELEASES:
To request your PR to be included in production software, please add the corresponding labels called "async-
+async-label <label1>, <label2>, !<label3> ...
This will add <label1>
and <label2>
and removes <label3>
.
The following labels are available async-2023-pbpb-apass3 async-2023-pbpb-apass4 async-2022-pp-apass6-2023-PbPb-apass2 async-2022-pp-apass4 async-2022-pp-apass4-accepted async-2022-pp-apass6-2023-PbPb-apass2-accepted async-2023-pbpb-apass3-accepted async-2023-pbpb-apass4-accepted async-2023-pp-apass4 async-2023-pp-apass4-accepted async-2024-pp-apass1 async-2024-pp-apass1-accepted async-2022-pp-apass7 async-2022-pp-apass7-accepted async-2024-pp-cpass0 async-2024-pp-cpass0-accepted
@ktf @aferrero2707 we would really need this to exercise SSS locally.
This PR did not have any update in the last 30 days. Is it still needed? Unless further action in will be closed in 5 days.