Jetty Releases 12.0.9
Jetty Versions: This release process will produce releases: 12.0.9
Target Date: May 1, 2024
Tasks:
- [x] Create the release(s) issue.
- [x] Update the target Jetty version(s) in the issue.
- [x] Update the target release date in the issue.
- [x] Link this issue to the target GitHub Project(s).
- [x] Assign this issue to a "release manager".
- [x] Review draft security advisories. Ensure that issues are created and assigned to GitHub Projects to capture any advisories that will be announced.
- [x] Update GitHub Project(s)
- [x] Create new project for the next releases (not this release).
- [x] Ensure new project is public (not private)
- [x] Freeze the target GitHub Project(s) by editing their names to "Jetty X.Y.Z FROZEN"
- [x] Review the issues/PRs assigned to the target GitHub Project(s). Any tasks that are not-yet-started are moved to next releases.
- [x] Review dependabot status. Manually run dependabot if needed and review resulting PRs for inclusion. Such updates should only be included in the week before a release if there is a compelling security or stability reason to do so.
- [x] Wait 24 hours from last change to the issues/PRs included in FROZEN GitHub Project(s).
- [x] Verify target project(s) are complete.
- [x] Verify that branch
jetty-10.0.xis merged to branchjetty-11.0.x. - [x] Assign issue to "build manager", who will stage the releases.
- [x] Create and use branches
release/<ver>to perform version specific release work from. - [x] Ensure
VERSION.txtadditions for each release will be meaningful, descriptive, correct text. - [x] Stage 12 release with Java 22.
- [x] Push release branches
release/<ver>to to https://github.com/eclipse/jetty.project - [x] Push release tags
jetty-<ver>to https://github.com/eclipse/jetty.project - [ ] Edit a draft release (for each Jetty release) in GitHub (https://github.com/eclipse/jetty.project/releases). Content is generated with the "changelog tool".
- [x] Create and use branches
- [ ] Assign issue to "test manager", who will oversee the testing of the staged releases.
- [ ] Test CometD.
- [ ] Test Reactive HttpClient.
- [ ] Test Load Generator.
- [ ] Test Jetty Docker images.
- [x] Test other Jetty OSS integrations.
- [x] Check TCK CI.
- [ ] Test sponsored integrations.
- [ ] Check CI for performance regressions.
- [ ] Notify interested parties and invite testing of the staged release(s).
- [ ] Assign issue back to "release manager".
- [ ] Collect release votes from committers.
- [ ] Promote staged releases.
- [ ] Merge release branches back to main branches and delete release branches.
- [ ] Verify release existence in Maven Central by triggering the Jenkins builds of CometD.
- [ ] Update Jetty versions on the website ( follow instructions in jetty-website ).
- [ ] Update (or check) Download page is updated.
- [ ] Update (or check) documentation page(s) are updated.
- [ ] Publish GitHub Releases.
- [ ] Prepare release announcement for mailing lists.
- [ ] Publish any security advisories.
- [ ] Edit
VERSION.txtto include any actual CVE number next to correspondent issue. - [ ] Edit any issues for CVEs in github with their CVE number
- [ ] Edit
- [x] Notify downstream maintainers.
- [ ] Eclipse p2 maintainer.
- [ ] Docker maintainer.
- [ ] Jenkins maintainer.
- [ ] Other maintainers.
Potential Staged release 12.0.9 now available at https://oss.sonatype.org/content/repositories/jetty-1886/
@joakime what's the ETA for this release?
@wendigo see https://github.com/orgs/jetty/projects/20 there are a few things discovered during testing that we are working on for this release.
Dropping Stage jetty-1886
Potential Staged Release 12.0.9 (stage 2, May 3rd) is now available at https://oss.sonatype.org/content/repositories/jetty-1887/
@joakime we've tested new staged release and can confirm that it works correctly and all of our tests are passing. Looking forward to promoting this build.
I'm considering this release complete.